Concrete Estimator

Estimate how much concrete a slab, a footing or wall strip, or a set of round columns needs. Pick the shape, enter the size and your own price per cubic yard to get cubic yards, bags and the concrete cost.

Free calculator • US customary units • Clear formulas • Last reviewed November 2026

Estimate your concrete

Choose a shape, enter your measurements and press Calculate. Results appear below the form.

Quick answer: A 20 x 20 ft slab that is 4 in thick needs about 4.94 cubic yards before waste. A 100 ft footing that is 16 in wide and 8 in deep needs about 3.29 cubic yards. Four round columns, 12 in across and 8 ft tall, need about 0.93 cubic yards.

Diagram of the concrete estimator formulas for a slab, a footing and round columns, with cubic yards equal to cubic feet divided by 27
The formula this calculator uses.

How the estimate works

Every shape is turned into cubic feet, then divided by 27 to get cubic yards, because one cubic yard is 27 cubic feet. The cost is the cubic yards times the price per cubic yard you enter, plus any delivery or short-load fee.

Slab: length x width x (thickness / 12)

Footing or wall strip: length x (width / 12) x (depth / 12)

Round columns: 3.1416 x (diameter / 24)² x height x number of columns

Waste is added as a percentage on top, and you choose the figure. An 80 lb bag yields about 0.60 cubic feet and a 60 lb bag about 0.45 cubic feet (QUIKRETE Concrete Mix No. 1101 data sheet), which is how the bag counts are found. For bigger jobs compare the cubic yards with a truck load using the yards of concrete in a truck page.

Examples

JobCubic feetCubic yards80 lb bags
Slab 20 x 20 ft, 4 in thick133.334.94223
Footing 100 ft long, 16 x 8 in88.893.29149
4 columns, 12 in across, 8 ft tall25.130.9342

All three rows use 0% waste. Add your own waste percentage in the calculator, and use your own price per cubic yard for the cost.

Sources and further reading

Frequently asked questions

How do I estimate how much concrete I need?

Convert the shape to cubic feet, divide by 27 for cubic yards, then add the waste you want. This estimator does that for a slab, a footing or wall strip, and round columns.

How many cubic feet are in a cubic yard?

One cubic yard is 27 cubic feet (3 ft x 3 ft x 3 ft).

How many bags of concrete are in a cubic yard?

Using the QUIKRETE Concrete Mix No. 1101 data sheet yields, an 80 lb bag makes about 0.60 cubic feet, so one cubic yard (27 cubic feet) needs about 45 bags. A 60 lb bag makes about 0.45 cubic feet, so about 60 bags.

Does the estimate include labor, forms or rebar?

No. The total is the concrete cost from the price and fees you enter. Forms, base, reinforcement, labor and finishing are extra.

How much waste should I add?

You choose the percentage. Uneven ground, spillage and over-excavation all use extra concrete, so many people add a margin. Ask your supplier what they recommend for your site.