Figuring yards of concrete takes one formula: length × width × thickness, all in feet, divided by 27. The result is cubic yards, the unit concrete is sold in. A 10 ft × 10 ft slab that is 4 inches thick works out to about 1.23 cubic yards.
The formula for figuring yards of concrete
Concrete is ordered by the cubic yard, but most measurements are taken in feet and inches. A cubic yard is 3 ft × 3 ft × 3 ft, so it holds 27 cubic feet. That is why the last step is always a division by 27.
- Cubic feet = length (ft) × width (ft) × thickness (ft)
- Thickness in feet = thickness in inches ÷ 12
- Cubic yards = cubic feet ÷ 27
How to figure yards of concrete, step by step
- Measure the length and the width of the area in feet.
- Measure the thickness in inches and divide by 12 to get feet. A 4 inch slab is 0.333 feet.
- Multiply length × width × thickness to get cubic feet.
- Divide the cubic feet by 27 to get cubic yards.
- Add a waste allowance and round up.
Example 1. A 15 ft × 10 ft pad that is 4 inches thick: 15 × 10 × 0.3333 = 50 cubic feet, and 50 ÷ 27 = 1.85 cubic yards.
Example 2. A 20 ft × 20 ft slab that is 6 inches thick: 20 × 20 × 0.5 = 200 cubic feet, and 200 ÷ 27 = 7.41 cubic yards.
Square feet to cubic yards chart
If you already know the area in square feet, you only need the thickness. These figures are cubic yards, before any waste allowance.
| Area | 4 in thick | 5 in thick | 6 in thick |
|---|---|---|---|
| 100 sq ft | 1.23 | 1.54 | 1.85 |
| 200 sq ft | 2.47 | 3.09 | 3.70 |
| 400 sq ft | 4.94 | 6.17 | 7.41 |
| 600 sq ft | 7.41 | 9.26 | 11.11 |
| 1000 sq ft | 12.35 | 15.43 | 18.52 |
A handy rule of thumb: every 100 square feet of slab needs about 0.31 cubic yards for each inch of thickness.
Figuring yards of concrete for round holes and tubes
For a round column, pier or tube, use the volume of a cylinder: π × radius² × height. Keep every measurement in feet. A tube that is 12 inches across (radius 0.5 ft) and 5 ft deep holds π × 0.5² × 5 = 3.93 cubic feet, which is 0.145 cubic yards. The concrete column calculator and the fence post concrete calculator do this for you.
How many bags of concrete are in a yard?
Using the published yield of QUIKRETE No. 1101, one cubic yard is 45 bags of 80 lb mix (0.60 cubic feet each) or 60 bags of 60 lb mix (0.45 cubic feet each). See how many 80 lb bags of concrete make a yard for a full chart.
How much extra concrete should I order?
Subgrade is rarely perfectly flat, so measure the thickness in several spots and use the average. A waste allowance of about 5 to 10 percent is a common planning assumption, not a standard. Round up to the next quarter or half yard, and ask your ready-mix supplier about their minimums.
Frequently asked questions
How do you figure yards of concrete?
Multiply length × width × thickness in feet to get cubic feet, then divide by 27. That is the same as figuring cubic yards of concrete for any rectangular slab, footing or pad.
How do you figure out a yard of concrete from square feet?
One cubic yard covers 81 square feet at 4 inches thick, 65 square feet at 5 inches and 54 square feet at 6 inches. Divide your area by that figure to see how many yards you need.
How many cubic feet are in a cubic yard?
27 cubic feet, because a cubic yard is 3 ft × 3 ft × 3 ft.
How do I convert square feet to yards of concrete?
Multiply the square feet by the thickness in feet, then divide by 27. For 100 square feet at 4 inches thick, that is 100 × 0.3333 ÷ 27 = 1.23 cubic yards.
How many yards of concrete do I need for a 10×10 slab?
A 10 ft × 10 ft slab needs about 1.23 cubic yards at 4 inches thick, 1.54 at 5 inches and 1.85 at 6 inches, before waste.
Is there a calculator for this?
Yes. Use the concrete yard calculator to convert feet and inches to cubic yards, or the concrete slab calculator. For a worked large example, see how many yards of concrete a 30×40 slab needs.
Related: How much is a yard of concrete? · Concrete Unit Converter · How many bags of concrete per square foot?
Ordering ready-mix? See how many yards of concrete are in a truck.